2020 CIPP Sewer Rehabilitation


updated 09/11/20 - 08:55am

The City of Mishawaka is embarking on our 10th annual Cured in Place Pipe (CIPP) Sewer Rehabilitation project. This year’s project was awarded to Inland Waters Pollution Control. To view an interactive map of the various locations in which this process will be completed this year, follow this link. To keep everyone up to speed on where work will be taking place, a weekly press release will be issued updating the progress and specific area scheduled to be complete.

CIPP is a trenchless (no digging) construction method in which a liner (soft piece of pipe) is installed inside the existing sewer pipe. The liner is then inflated, steamed and cured. Once cured, the liner is as strong and durable as a new piece of pipe. Prior to the lining process, equipment and workers will be on site to clean and video the existing sewer pipes.

On rare occasions during the lining process, a distinctive resin-like odor (similar to a nail salon) may be detected in nearby homes and businesses. The odor is not an indicator of danger, and should dissipate quickly if exposed to air. Typically, the odor enters through a pipe without a trap, or one that has a dried out trap. To be proactive, we ask owners to fill any floor drains and/or traps with a bucket of water to reduce the possibility of this odor entering their home or business. If this does not resolve the issue, the owner shall contact the contractor via their phone number listed below. The odor is typically limited to the block of the actual lining, but on rare occasion may travel through the liner to further locations.

Questions regarding this work may be directed to Sean Bergman of Inland Waters Pollution Control at (574) 400-6142.

 

Work Date & Location*

last updated 09/11/20 - 08:55am

Date Location
Sep 14 E. Third St between Merrifield Ave and Wenger Ave
Sep 15 Clay St between W Edgar St and W Lowell Ave
W. Broadway between Calhoun St and Webster St
Sep 16 E. Sixth St from Main St to Dead End
Sep 17 Normandy Dr from Leyte Ave to Bastogne Ave
Normandy Dr from Palau Ave to Ardennes Ave
Sep 18 Marrett Dr from Norfolk Ct to Bennington Dr

Sep 8-10 Jefferson Blvd between Merrifield Ave and N. Byrkit Ave

Aug 31-Sep 2 Jefferson Blvd between Merrifield Ave and N. Byrkit Ave
Sep 3-4 Grape Rd between Day Rd and Douglas Rd

* weather permitting